"Touted as “America’s first offshore wind project,” Cape Wind became one of America’s most high-profile and most controversial wind-energy projects.
Now, it may be “dead in the water.”
On January 6, the two power companies, National Grid and Northeast Utilities, that had agreed to purchase most of the electricity Cape Wind was to generate, terminated their contracts with the developers due to missed milestones.
Under the terms of the contracts, Cape Wind had to secure financing and give notices to proceed to its suppliers to start work by December 31, 2014.
Neither happened and both companies filed to cancel power purchase agreements.
“The project is in cardiac arrest,” according to Amy Grace, a wind-industry analyst with Bloomberg New Energy Finance."